Gotland D Cabin
Three days for two carpenters completed the sub-floor. Four days for four carpenters to erect the cabin.
-
Langeoog Cabin
The sub-floor bearer kit took two carpenters eight hours including setting out and concreting (concrete was delivered). The cabin took us two full days including boron treatment with three carpenters. The add-on deck measured 3.9m x 2.3m took one carpenter 6.5 hours including the installation of four steps with steel stringers.